Photo sets from Library, Parks & Recreation and Community Theater / Council Chamber.

Steel Erection at LPR SiteSteel Erection
Below Grade Plumbing Installation in Building PadBelow Grade Plumbing
LPR Site Gridline 1-5Steel Structure
Welding Steel at LPR Building Level 3Welding
Steel Installed at LPR Parking GarageSteel Structure
Steel Decking at 2nd Floor Lobby EntranceSteel Decking
Steel Installed at LPRSteel Installation
Crane Erecting Steel at RoofCrane
Park Side of LPR Steel StructureLPR Steel Structure
Welding Steel at Building Level 2Welding
Steel Erection at Council ChambersSteel Erection
LPR Steel BuildingSteel Building
Steel Erection at LPR SiteSteel Erection
Below Grade Plumbing Installation in Building PadBelow Grade Plumbing
LPR Site Gridline 1-5Steel Structure
Welding Steel at LPR Building Level 3Welding
Steel Installed at LPR Parking GarageSteel Structure
Steel Decking at 2nd Floor Lobby EntranceSteel Decking
Steel Installed at LPRSteel Installation
Crane Erecting Steel at RoofCrane
Park Side of LPR Steel StructureLPR Steel Structure
Welding Steel at Building Level 2Welding
Steel Erection at Council ChambersSteel Erection
LPR Steel BuildingSteel Building
Rebar Installation at LPR SiteRebar Installation
2nd Concrete Pour for LPR Building FoundationConcrete Pour
Rebar Installation at Retaining WallRebar Installation
LPR Site Gridline 9-ENDLPR Site
Rebar Installation at Retaining WallRebar Installation
Rebar Installation at Pile CapsRebar Installation
3rd Concrete Pour for LPR Building FoundationConcrete Pour
Below Grade MEP Installation in Building PadBelow Grade MEP
Below Grade Plumbing Installation in Building PadBelow Grade Plumbing
Shooting Shotcrete at Retaining WallShotcrete
Rocking Building Pad: Gridline 1-5LPR Building Pad
Steel Delivered to LPR Site for Steel ErectionSteel Delivery
Chipped Piles along Shoring Wall at LPR SiteChipped Production Piles
Excavation of Piles and Elevator Pit for Building FoundationElevator Pit
Joint Trench Work in Antoinette LaneJoint Trench
Below Grade Waterproofing PreparationBelow Grade Waterproofing
Below Grade Waterproofing Installed Along Shoring WallBelow Grade Waterproofing
Excavation of Piles for Building FoundationExcavation
Rebar Installation along Shoring WallRebar Installation
Double Cased Auger Cast PilesAuger Cast Piles
Installing EPS foam in FoundationEPS Foam Installation
LPR Site Gridline 1-5LPR Site
Rebar Installation at LPR SiteRebar Installation
1st Concrete Pour for LPR Building FoundationConcrete Pour
Drill Tech drilling piles for building foundation at LPR SiteProduction Piles
Concrete curing in Auger Cast Piles with CagesAuger Cast Piles
Production Piles at LPR SiteProduction Piles
Joint Trench Work in Sidewalk along Antoinette LaneJoint Trench
Joint Trench excavation work in roadwayJoint Trench
Joint Trench Underground Utility on Antoinette LaneJoint Trench
Drilling Piles - Deep FoundationsProduction Piles
Installation of below grade waterproofing at shoring wallBelow Grade Waterproofing
Watering LPR Site for Dust ControlDust Control
Grading and Building Pad CertificationBuilding Pad
Joint Trench underground utilities within LPR SiteJoint Trench Within LPR Site
Excavation of Elevator PitElevator Pit
Storm Drain installation in the geofoam areaUtilities in Geofoam Area
Drill Tech places auger cast pileAuger Cast Pile
Auger Cast Piles in LPR SiteLPR Site
Cages onsite for production pilesProduction Piles
Underground utilties in geofoam areaLPR Site
Drill Tech Subcontractor prepping auger cast piles for testingTest Pile Preparation
Compression Test: Auger Cast PileTest Pile Testing
Tension Test: Auger Cast PileTest Pile Testing
Compaction in the geofoam areaGeofoam Installation Complete
Auger Cast Pile DrillingDrilling Piles
After drilling, Drill Tech places auger cast pileAuger Cast Pile
Pouring concrete to keep auger cast pile in placeAuger Cast Pile
Excavation along El Camino RealHillside Along ECR
Excavation of temporary BART access road on LPR SiteBART Access Road
Temporary BART Access Road CompleteBART Access Road
Site Demolition and GradingLPR Site
Excavating LPR Site for Geofoam installationGrading and Excavation
Shoring Bench along El Camino RealShoring Bench
Installing Soldier Beams on Shoring BenchShoring Wall
Sewer Line InstallationSewer Pipe
Relocation of Storm Drain UtiltiesStorm Drain
Excavating lift 4 of shoring wall along ECRShoring Wall
Prepping Shoring wall for wood lagging installationShoring Wall
Storm Drain Pipe InstallationStorm Drain Utilties